Cleanup of contaminated soil at a shipyard shipyard in Virginia – closure report

The project initiated in 2005 was treated with AgroRemed resulted in the recovery of 140 gallons of free product mobilized through bacterial action and after a final application of AgroRemed in 2007 was closed by the VA DEQ based on the analysis report of 22nd April, 2008.

Contaminated area at the shipyard

The Pollution complaint # 05-5160 has been closed by the VA DEQ.

Showing_trenches_below_AST